While working for Pacific Architect & Engineer's Antarctic Support Contract there were several large projects completed by the Fuels Department during the 2019/2020 season.

Hose Lay Project

Hose Lay Project

Hose Lay Project

Hose Lay Project
1/4
William's Airfield Hose Lay
SCOPE: Deploy 7 miles of hose from the base of the station to Williams Airfield on the ice shelf ensuring all connections are secure before transferring fuel to 12 aviation fuel tanks.
​
PROJECT TIMELINE: Sep 2019 - Oct 2019

Tanker Project

Tanker Project

Tanker Project

Tanker Project
1/4
Tanker
SCOPE: Offload 7 million gallons of fuel from Maersk Peary Tanker to McMurdo Station bulk fuel tanks while maintaining fuel containment throughout offload process.
​
PROJECT TIMELINE: Feb 2020 (52 hours)